Project monitoring and control process is an important process in developing any
computer information system. Monitoring and Control provides an understanding
of the project’s progress so that when the project deviates significantly from
the plan appropriate corrective actions can be taken. This research
will identify general measures for the specific goals and its specific
practices of Project Monitoring
and Control Process Area in Capability Maturity Model Integration
(CMMI).CMMI is developed in USA by Software Engineering Institute (SEI) in Carnegie
Mellon University. CMMI is a framework for assessment and improvement
of computer information systems. The procedure we used to determine the
measures is to apply the Goal Questions Metrics (GQM) approach to the two specific
goals and its ten specific practices of Project Monitoring and Control Process Area in CMMI.